Traffic Signal Refurbishment Programme – GHE Post Covid-19

Infrastructure has advised their programme of work scheduled for traffic signals and junctions for 2020. They will endeavour to complete work as quickly as possible and will advise any changes that may occur to the schedule.

Please check below and note any work which is likely to affect the routes you take during August.

 

Saville Street Junction – (1 Team / 4 days / 1 week)

24th – 28th August.

This will involve the complete shutdown of the junction for 4 to 5 days as the ageing traffic signal

heads and controller are removed and replaced with new equipment. During that short period there

will be no crossing facilities available to any users in the vicinity who may need it. During the hours

of 8.00am – 5.30pm there will be installation engineers on site to assist anyone crossing that junction. Outside of those times the junction will be unmanned.

 

New Street / Union Street Junction – (1 Team 3 – 4 days/ less than a week)

29th August – 31st August

This will involve the complete shutdown of the junction for 3 to 4 days as the ageing traffic signal

heads and controller are removed and replaced with new equipment. During that short period there

will be no crossing facilities available to any users in the vicinity who may need it. During the hours

of 8.00am – 5.30pm there will be installation engineers on site to assist anyone crossing that junction. Outside of those times the junction will be unmanned.

traffic-lights